General Contracting

As a General Contractor, we will provide an Owner / Client with a tendered price to complete all work in accordance to the engineered drawings and specifications. We will also provide competent project managers and site superintendent to manage and complete the project

Alloy Collision Center

Saskatoon SK

  • Construction of a new 57,500sq ft main floor and 8,500sq ft 2 floor collision center in Saskatoon.

  • Timber piles with structural steel, masonry, structural steel studs, cladding and curtain wall exterior.

  • Slab on grade and structural slabs throughout the building.

  • All underground utilities and new asphalt parking lot for the Alloy Collision Center and Spiffy Car Wash.

Avenue P Medical Office Building

Saskatoon SK

  • Construction of a four storey concrete building and underground parkade. Completed the tenant improvements on 3 of 4 floors.

  • Due to an extremely congested work area we were unable to use a tower crane for the construction

  • The EFCO forming system was used for all the concrete.

Alloy Collision Center

Location: Saskatoon Sk

Client: Vaughn Wyant Investments Inc.

Spadina Lift Station Bypass Building

​Saskatoon SK

Construction of a new bypass lift station complete with :

  • Installation of a new 1200mm diameter pipe from the new wet well to diversion manhole.

  • Due to the spoil conditions a shoring system was installed.

  • All process mechanical, electrical and control systems were included.

Alloy Collision Center

Location: Saskatoon Sk

Client: Vaughn Wyant Investments Inc.

Island Falls Concret Rehabiltation  ​- Phase 2 & 4 & 6

Island Falls SK

​​​​​Work at 'A' Dam:

  •  Dredging at west abutment

  •  Installation of sheet piles and reinforced concrete infill

  •  Extension of east pier

Work at 'Main' Dam:

  •  Removal of existing conduit, handrail, concrete curb, steel scrap and timber stoplogs

  •  Corbel construction on underside of existing deck

  •  16" concrete topping to entire deck

  •  New crane rails

  •  Lift and roll gantry crane and stop log lifter onto new concrete deck

  •  Conduit, lighting, electrical distribution, grating, handrail and fencing

  •  Misc. Repairs to upstream deck face

  • Concrete restoration on main dam piers and new concrete coatings

  • Reinforcing the rail beams

  • New concrete slab for the stoplog lift

Alloy Collision Center

Location: Saskatoon Sk

Client: Vaughn Wyant Investments Inc.

St. Thomas More College - Cafeteria and Library Addition

​Saskatoon SK

  • Expansion of St. Thomas More’s cafeteria and library along with additional student centered space including a new lounge and student services hub. 

  • A new 5 storey elevator was installed to provide total access throughout the college and an existing elevator was removed and filled in for office use.

  • Recipient of the 2018 Municipal Heritage Awards Program: Award of Merit “Sensitive Addition”
     

Alloy Collision Center

Location: Saskatoon Sk

Client: Vaughn Wyant Investments Inc.

Waskesiu Marina Dock & Infrastructure Replacement

​Waskesiu SK

  • Remove existing docks and wood timber piles prior to the ice forming.

  • Engineer and build the ice in the harbor to the engineered thickness.

  • Supply and install the new pipe piles through the ice. 

  • New docks were installed on top of the ice and set in place during the spring thaw.

  • Misc. lighting revisions

Alloy Collision Center

Location: Saskatoon Sk

Client: Vaughn Wyant Investments Inc.

Landfill Gas Collection System

​Saskatoon SK

Supply and installation of:

  •  850 lm of 300mm diameter header pipe and 250mm diameter utilization pipe around the City of Saskatoon the landfill.

  • 100mm and 200mm diameter lateral pipe from the main header line to the 29 wells installed thru out the landfill.

  • A 225m2 pre-engineered Blower Flare Station complete with all process mechanical and electrical, condensate
    chamber, and installation of Owner supplied dryer/chiller system and Flare.

  • A new 315 m2  pre engineered power generation facility adjacent to the landfill
    complete with the installation of 2 - 800 kWe.

  • Owner supplied engine generator sets and all process mechanical and electrical.

317 103 St E, Saskatoon, SK S7N 1Y9, Canada          

p: (306) 477-5520                        

e: info@allanconstruction.ca

2018 Allan Construction 

  • Instagram Social Icon
  • Facebook Social Icon
  • Twitter Social Icon
  • YouTube Social  Icon